Skip to main content

Toll Free: (800) 407-2217     Pay By Phone: 1-844-968-1966

VOTE NOW
Quick Bill Pay
Contact Us
Report an Outage Report an Outage
SmartHub Login
Home
Menu
  • To report an outage call 800-407-2217 or 620-397-5327.

 
  • Home
  • Member Center
    • Manage My Account
      • SmartHub
      • Bill Pay Options
        • Pay Ahead Power Program
      • Understanding Your Bill
      • Late and Delinquent Bills
      • New Service, Transfers and Disconnects
      • Update Your Contact Information
      • Member Handbook
    • Payment Assistance
      • LIEAP
      • Payment Arrangements
      • Kansas Weatherization Program
      • Payment Assistance Resources
      • Efficient Energy
  • Your Community
    • Community Commitment
    • Youth Tour and Cooperative Leadership Camp
    • Scholarship Opportunities
    • CoBank Sharing Success Grant Program
  • Cooperative Information
    • About Lane-Scott Electric
      • Lane-Scott Electric Profile
      • Meet Our Team
      • History
      • Rates
      • Bylaws
      • Annual Meeting
      • Employment Opportunities
    • General Info
      • Capital Credits
      • Cold Weather Rule
      • Understanding Demand
      • Distributed Generation
      • Advanced Metering Infastructure
      • Board of Trustee Election Information
      • Contact the Board of Trustees
  • News and Communication
    • Lane-Scott Electric Newsletter
    • Receive Email and Text Message Notifications
    • In the News
    • Members Satisfaction Survey Results
  • Electric, HVAC Service and Supply Department
    • Services and Retail Store
    • Generac Generators
  • Outages and Safety
    • Outages
      • Outage Center
      • Outage Map
    • Safety
      • Dig Safe and KS One Call
      • Power Line Safety
      • Safety on the Farm
      • Generator Safety
      • Trees and Power Lines
      • Electrical Safety Demonstrations
    • Staying Prepared: Energy Emergency Alerts Explained

Johnson Corner Solar Project Update

Update 1.30.2020

Story provided by Steve Hausler, Sunflower Electric Power Corporation

200122%20JCSP%200452-350x143.jpg

Sunny days that will soon be transformed into electricity are also keeping the construction progress of the Johnson Corner Solar Project on schedule. The project is being built in Stanton County near the town of Johnson City.

Construction of the 20 megawatt (MW) solar farm, owned and operated by Lightsource BP, is in full swing with about 200 construction contractors currently on site. As of Jan. 20, crews had completed construction of 366 of the 893 tracker rows and installed 18,182 of the 75,012 solar panels that will be installed on the site.

Sunflower will purchase the power from this Lightsource BP project, which upon completion will be the largest solar farm in Kansas. Lightsource BP is one of the largest owners and operators of solar power facilities in the world and the project at Johnson Corner is one of their first projects in North America.

The location of the site in the far southwest corner of Kansas was chosen since the area has the highest level of solar irradiance in the state. Solar irradiance is a measure of the rate at which solar energy falls onto a surface, like a solar panel that absorbs the sun’s rays and converts them into electricity.

The location of the solar project will also provide a solution to a transmission issue in the area according to Sunflower’s Corey Linville, vice president of power supply and delivery.

“The Syracuse-Bear Creek 115 kV transmission line just north of Johnson Corner is nearing its facility rating limit and would have been in need of a $8-12 million upgrade,” Linville said. “The injection of energy from JCSP at Johnson Corner will ease loading on this line and defer or eliminate the need for the upgrade.”

The project is expected to be energized in late March or early April.

    200122%20JCSP%200516-315x220.jpg

Update 1.17.2020

Johnson%20Corner%20Solar%20Project_winter2019currentweb-1000x1545.jpg

Submitted by Ann Marie Jennings on Thu, 12/19/2019 - 11:04

Back to Top

Quick Links

  • Contact Us
  • Contact the Board of Trustees or Request to Attend a Board Meeting
  • News
  • Privacy Policy
  • Trustee Login
  • SmartHub Login

 

Co-ops-Vote_SquareBlue.jpg

 

Vets_Power_Us_logo_300x300.png

Follow Us Online

©2025 Lane-Scott Electric Cooperative. All Rights Reserved.

  • Home
  • Member Center
    • Manage My Account
      • SmartHub
      • Bill Pay Options
        • Pay Ahead Power Program
      • Understanding Your Bill
      • Late and Delinquent Bills
      • New Service, Transfers and Disconnects
      • Update Your Contact Information
      • Member Handbook
    • Payment Assistance
      • LIEAP
      • Payment Arrangements
      • Kansas Weatherization Program
      • Payment Assistance Resources
      • Efficient Energy
  • Your Community
    • Community Commitment
    • Youth Tour and Cooperative Leadership Camp
    • Scholarship Opportunities
    • CoBank Sharing Success Grant Program
  • Cooperative Information
    • About Lane-Scott Electric
      • Lane-Scott Electric Profile
      • Meet Our Team
      • History
      • Rates
      • Bylaws
      • Annual Meeting
      • Employment Opportunities
    • General Info
      • Capital Credits
      • Cold Weather Rule
      • Understanding Demand
      • Distributed Generation
      • Advanced Metering Infastructure
      • Board of Trustee Election Information
      • Contact the Board of Trustees
  • News and Communication
    • Lane-Scott Electric Newsletter
    • Receive Email and Text Message Notifications
    • In the News
    • Members Satisfaction Survey Results
  • Electric, HVAC Service and Supply Department
    • Services and Retail Store
    • Generac Generators
  • Outages and Safety
    • Outages
      • Outage Center
      • Outage Map
    • Safety
      • Dig Safe and KS One Call
      • Power Line Safety
      • Safety on the Farm
      • Generator Safety
      • Trees and Power Lines
      • Electrical Safety Demonstrations
    • Staying Prepared: Energy Emergency Alerts Explained